Past Projects of J.E. McAmis
Marine Construction and Dredging
J.E. McAmis maintains a modern fleet of ABS classed dredging equipment, barges, tugboats and support vessels. J.E. McAmis has taken on difficult hard rock dredging projects from the most remote areas of the Bering Sea to some of the busiest ports in the United States. Dredging capabilities range from routine maintenance of ports, harbors and waterways, to highly specialized precision consolidated dredging as well as dredging performed in conjunction with drilling and blasting. J.E. McAmis has completed millions of cubic yards of difficult dredging during construction and maintenance of ports, harbors and waterways throughout the United States.
Description
Project Specifications
- Agency: U.S. Army Corps Of Engineers, Portland District
- Contract Price: $10,000,000
- Completion: 2008
- Key Elements: Consolidated Materials Dredging, In-water Disposal, Upland Disposal
Description
Marina del Rey, considered the largest man-made marina in the world sits just north of the Port of Los Angeles and just to the south of Venice Beach. In 2007, J.E. McAmis removed more than 255,000 cubic meters of material from the entrance channel of Marina del Rey and transported the material via dump barge to a near shore disposal area adjacent to Dockweiler Beach.
Project Specifications
- Agency: U.S. Army Corps of Engineers, Los Angeles Dist.
- Contract Price: $2,398,750
- Completion: 2007
- Key Elements: Maintenance Dredging, Ocean Disposal
Description
The Riverbed Gradient Facility, Sacramento California. Over 180,000 cubic yards of cementitious river rock was excavated. Approximately 240,000 tons of riprap was placed between a series of sheetpile walls which formed the cells to create the gradient structure. The primary focus of this project was to create a 1,500 x 750 foot structure to protect migrating salmon from nearby intake pumps used by a local irrigation district.
Project Specifications
- Agency: U.S. Army Corps of Engineers, Sacramento District
- Contract Price: $13,000,000
- Completion: 2001
- Key Elements: Excavation of Cemented Rock, Rip-Rap Installation, Sheetpile Installation, Endangered Species Protection, Habitat Protection and Construction
Description
The North Jetty Sand Tightening and Extension Project at Cape Canaveral, FL, consisted of reconstruction of the existing North Jetty and extending the jetty an additional 300'. The project required driving a sheetpile wall down the center of the new jetty alignment and placement of over 39,000 tons of granite armor stone ranging up to 16 tons in size. The primary purpose of the project was to stop the migration of sand into the entrance of Canaveral Harbor.
Project Specifications
- Agency: U.S. Army Corps of Engineers Jacksonville District
- Contract Price: $6,500,000.00
- Completion: 2005
- Key Elements: Jetty Construction, Sheetpile Wall Installation
Description
The Ice Harbor Dam Project on the Columbia River consisted of drilling, blasting and dredging more than 115,000 cubic yards of Basalt in more than 20 feet of water. With drilling, blasting and dredging operations taking place only 100 feet from the face of Ice Harbor Dam, vibration control was a vital project component. Working around the clock in difficult seismic and environmental conditions, J.E. McAmis was able to successfully deliver the project 15% ahead of schedule with a zero incident, safety and environmental record.
Project Specifications
- Agency: U.S. Army Corps of Engineers, Walla Walla District
- Contract Price: $3,700,000.00
- Completion: 1992
- Key Elements: Drilling and Blasting, Hard Rock Excavation, Vibration Monitoring and Control
Description
The Port of Anchorage Maintenance Dredging Project was completed in 2000. J.E. McAmis dredged approximately 1.9 million cubic yards in heavy ship traffic, and in 38 foot tides and extreme currents.
Project Specifications
- Agency: U.S. Army Corps of Engineers, Alaska District
- Contract Price: $9,500,000.00
- Completion: 2000
- Key Elements: Approximately 1.9 Million Cubic Yards of Material Dredged, 38 Foot Tides, 9 Knot Currents, High Traffic Shipping Area
Description
St. Paul Island, AK Harbor Improvements Phase II is located in one of the most harsh and remote environments in the Bering Sea. J.E. McAmis' PC 3000 Dipperdredge, Megan-Renee, excavated more than 400,000 cubic yards of hard rock, cemented boulders and sand, as a subcontractor to Kelly-Ryan Construction of Seattle, WA. The dredge crew worked around the clock in extreme sea conditions to bring the project home on time and within budget.
Project Specifications
- Agency: U.S. Army Corps of Engineers, Alaska District
- Contract Price: $11,000,000.00
- Completion: 2005
- Key Elements: Hard Rock Dredging, Cemented Boulder Dredging, Sand Removal, Ocean Disposal
- Subcontractor To: Kelly-Ryan, Seattle WA
Description
The Osprey Platform Pipelines Stabilization Project was performed in the Cook Inlet, AK for the Forest Oil Company. The objective of the project was relocation and stabilization of three (3) high pressure production lines, without interrupting production. Stabilization was achieved by relocating the lines into a series of trenches which were constructed by dredging through a rock formation which lay between the Osprey Platform and the terminus point. This project required precise positioning and hydraulic control.
Project Specifications
- Agency: Forest Oil Company
- Contract Price: Undisclosed
- Completion: 2006
- Key Elements: Hard Rock Dredging, Pipeline Relocation and Placement
Description
The Interim Corner Cut-off project was performed for the Canaveral Port Authority by J.E. McAmis, and consisted of approximately 225,000 cubic yards of upland excavation and another 300,000 cubic yards of dredging. The upland material was utilized to construct an embankment and spoil dike system. The dredged material was disposed of off shore in the Canaveral Ocean Dredged Material Disposal Site. The project included sheet pile wall demolition, sheet pile wall modifications and installation of approximately 12,000 square feet of sheet pile along a portion of the new bank alignment. The project also included placement of rip-rap slope protection, and the construction of several concrete outfall structures.
Project Specifications
- Agency: Canaveral Port Authority
- Contract Price: $8,000,000.00
- Completion: 2009
- Key Elements: Dredging, Ocean Disposal, Upland Containment Facility Construction, Ordnance Screening and Disposal
Description
Work entailed raising approximately 450 linear feet of the existing North Jetty to El. +8.0 feet MLLW. Construction included the manufacture and installation of marine mattresses, placement of geotextiles, bedding stone and 13,000 tons of up to 15 ton armor stone. Work also included the installation of two USCG fixed navigation lights and daymarks. There was no land access to site and all work was accomplished using ABS floating equipment.
Project Specifications
- Agecny: U.S. Army Corps of Engineers, Jacksonville District
- Contract Price: $5,100,000
- Completion: 2009
- Key Elements: Marine Mattress Installation, Jetty Rehabilitation